Street Improvements - County Road 151

151 concept plan 2

Contractors are approximately 90% complete with the roadway sections between Washington Street and Hampton Court.  The water line and sewer lines are complete and in service.  Contractors are currently working on drainage and grading for the section of paving between Hampton Court and the SH 34 bypass.  To date this project is approximately 49% complete.  The total project construction time was for 500 days.  The contractor has currently worked 72 days and projects the project to be complete in less than 300 days.

12-1-17