Municipal Facility - Joint City Hall/PD Complex

Kaufman City Hall [front door cam] B06Estimated Completion Date - August, 2018

Progress Report - 12/5/2017

Site work:

  • East paving poured
  • Washington & Cherry sidewalks - graded
  • Telephone pole set and underground conduits - complete

Building:

  • Should be dried in by Christmas
  • Roof deck - complete
  • Clerestory framing - complete
  • Exterior wall framing - 95%
  • Interior wall framing - 40%
  • Raised slab - complete
  • Overhead electrical - 45%
  • Overhead ductwork - 50%
  • Overhead plumbing - 10%
  • Brick - 5%

Safety:

  • No accidents to report
  • No incidents to report

Lost Days:

  • No lost days to report

Schedule Review:

  • Continue roofing
  • Complete exterior wall framing
  • Generator pad - this week
  • Continue overhead MEP
  • Continue interior wall framing
  • Continue brick
  • Pour sidewalks this week

12-1-17

City Hall Aerial 1