Municipal Facility - Joint City Hall/PD Complex

Kaufman City Hall [front door cam] B06

Estimated Completion Date - August, 2018

6/19/2018:

SITEWORK

  • Irrigation - complete
  • Sandblast plaza paving - this week
  • Planting - this week
  • Sod - next week

BUILDING

  • Metal panels - complete
  • Countertops - complete
  • Final paint - complete
  • Terrazzo floor - complete
  • VCT - complete
  • Carpet - complete
  • Plumbing fixtures - complete
  • Electrical fixtures - complete
  • Window treatments - complete
  • Finish doors & hardware - complete
  • AV final connection - complete (less TV install / after final clean)
  • Windows - 99%
  • Millwork - 99%
  • Toilet partitions & accessories - 95%
  • Install canopies - 75%
  • Install lockers - 80% (completes Friday, 6/22)

SAFETY

  • No accidents to report
  • No incidents to report

LOST DAYS

  • No lost days to report.

SCHEDULE REVIEW

  • Plaza sand blasting
  • Terrazzo base
  • Mechanical screens
  • Planting & sod

5-22-18

2018.05_01