Municipal Facility - Joint City Hall/PD Complex

Kaufman City Hall [front door cam] B06

Estimated Completion Date - August, 2018

SITEWORK

  • Madison & South St. ready for asphalt
  • Sidewalks - on hold until brick is complete

BUILDING

  • Metal roofing - 40% TPO - 95% complete
  • Interior wall framing - complete
  • Overhead electrical - 95%
  • Brick 60%
  • Tape & bed - 95% Area A.  20% Area B
  • Texture & paint - 90% Area A
  • Ceiling Grid A - started

SAFETY

  • No accidents to report
  • No incidents to report

LOST DAYS

  • Four lost days to report - 2/6, 2/7, 2/12 & 2/13.  Cold and wet weather conditions.

SCHEDULE REVIEW

  • Continue metal roofing
  • Texture & IST coat walls - Area B
  • Continue ceiling grid
  • Install light fixtures
  • Start epoxy flooring
  • Continue brick
  • Asphalt balance next dry dayCIP - 2-8-18