Municipal Facility - Joint City Hall/PD Complex

Kaufman City Hall [front door cam] B06

Estimated Completion Date - August, 2018

4/10/18:

SITEWORK

  • Sidewalks - 60%

BUILDING

  • Roofing - complete
  • Metal panels - 95%
  • Windows - 98%
  • Brick - complete
  • Tape & bed - complete 
  • Texture & paint - 98%
  • Lighting - complete
  • A/C grills - complete
  • Millwork - 75%
  • Terazzzo - starts 4/25/18

SAFETY

  • No accidents to report
  • No incidents to report

LOST DAYS

  • No lost days to report.

SCHEDULE REVIEW

  • Complete painting
  • Install doors & hardware
  • Complete millwork installation
  • Complete windows
  • Install fencing
  • Continue sidewalks
  • Complete metal coping
  • Start canopies
  • Final grading
  • Start landscaping / irrigation
  • Start VCT & carpet

3-28-18

2018.04_01